Gold Line Update: Azusa Avenue Closure Begins Soon

Expect more street closures as Gold Line construction continues throughout the San Gabriel Valley.

From the Gold Line Construction Authority:

Lane Closures on Santa Anita Ave. - Arcadia to Start
end of April/beginning of May 2013
Construction of the new bridge over Santa Anita Ave. is anticipated to begin at the end of April/beginning of May; following completion of work on Colorado Boulevard. This work requires long-term lane closures on north and southbound Santa Anita Avenue. The lane closures will continue through the end of October 2013. A construction notice is forthcoming.
Click here to view Arcadia construction activity map.

Full Closure of Azusa Ave. - Azusa to start April 29, 2013

Crews will be constructing grade crossing improvements at Azusa Avenue between 9th Street and Foothill Boulevard. This work requires a full closure of Azusa Avenue at the railroad crossing through mid-July 2013. This work is anticipated to begin on April 29, 2013. A construction notice is forthcoming.
 Click here to view Azusa construction activity map.

Colorado Blvd. - Arcadia to Re-open by the End of April 2013
Work is nearing completion on the new railroad bridge over Colorado Boulevard. Although the main superstructure has not yet arrived, Colorado Boulevard is anticipated to re-open to traffic by the end of April 2013. A future one-day closure of Colorado Boulevard is anticipated to install the superstructure.

REMINDER: Ongoing Construction Activity

California Ave. - Monrovia: Mar. 9 through July, 2013
Construction of the grade crossing improvements on California Avenue at the railroad corridor will continue through the end of July 2013.
Click here to view construction notice.
Click here to view Monrovia construction activity map.

Foothill Blvd. - Azusa: Jan. 14 through Sept. 2013
Construction of new bridges over Foothill Boulevard continues. This work requires lane closures on east and westbound Foothill Boulevard from January 14, 2013 through the end of September 2013.
Click here to view construction notice. Click here to view Azusa construction activity map.

Palm Dr. - Azusa: Jan. 7 - May 3, 2013
Crews continue work on the two new light rail bridges over Palm Dr. in Azusa, requiring a full closure of the street at the railroad corridor through May 3, 2013.
Click here to view construction notice. Click here to view Azusa construction activity map.

Find out what's happening in Glendorawith free, real-time updates from Patch.

Dalton Ave. - Azusa: Feb. 19 - Late May, 2013
Due to unexpected issues, work has been extended on the grade crossing improvements on Dalton Avenue at the railroad corridor until late May 2013 (updated construction notice below).Click here to view construction notice.Click here to view Azusa construction activity map.